Verification typically involves reviews and meetings to evaluate documents, plans, code, requirements, and specifications. This can be done with checklists, issues lists, walkthroughs, and inspection meetings. Validation typically involves actual testing and takes place after verifications are completed. The term 'IV & V' refers to Independent Verification and Validation.


Concepts and Definitions


Software Verification and Validation (V&V) is the process of ensuring that software being developed or changed will satisfy functional and other requirements (validation) and each step in the process of building the software yields the right products (verification). The differences between verification and validation are unimportant except to the theorist; practitioner’s use the term V&V to refer to all of the activities that are aimed at making sure the software will function as required.

V&V is intended to be a systematic and technical evaluation of software and associated products of the development and maintenance processes. Reviews and tests are done at the end of each phase of the development process to ensure software requirements are complete and testable and that design, code, documentation, and data satisfy those requirements.

Activities

The two major V&V activities are reviews, including inspections and walkthroughs, and testing.

1) Reviews, Inspections, and Walkthroughs

Reviews are conducted during and at the end of each phase of the life cycle to determine whether established requirements, design concepts, and specifications have been met. Reviews consist of the presentation of material to a review board or panel. Reviews are most effective when conducted by personnel who have not been directly involved in the development of the software being reviewed.

Informal reviews are conducted on an as-needed basis. The developer chooses a review panel and provides and/or presents the material to be reviewed. The material may be as informal as a computer listing or hand-written documentation.

Formal reviews are conducted at the end of each life cycle phase. The acquirer of the software appoints the formal review panel or board, who may make or affect a go/no-go decision to proceed to the next step of the life cycle. Formal reviews include the Software Requirements Review, the Software Preliminary Design Review, Software Critical Design Review, and the Software Test Readiness Review.

An inspection or walkthrough is a detailed examination of a product on a step-by-step or line-of-code by line-of-code basis. The purpose of conducting inspections and walkthroughs is to find errors. The group that does an inspection or walkthrough is composed of peers from development, test, and quality assurance.

2) Testing

Testing is the operation of the software with real or simulated inputs to demonstrate that a product satisfies its requirements and, if it does not, to identify the specific differences between expected and actual results. There are varied levels of software tests, ranging from unit or element testing through integration testing and performance testing, up to software system and acceptance tests.

a. Informal Testing

Informal tests are done by the developer to measure the development progress. "Informal" in this case does not mean that the tests are done in a casual manner, just that the acquirer of the software is not formally involved, that witnessing of the testing is not required, and that the prime purpose of the tests is to find errors. Unit, component, and subsystem integration tests are usually informal tests. Informal testing may be requirements-driven or design-driven. Requirements-driven or black box testing is done by selecting the input data and other parameters based on the software requirements and observing the outputs and reactions of the software. Black box testing can be done at any level of integration.

b. Formal Testing

Formal testing demonstrates that the software is ready for its intended use. A formal test should include an acquirer- approved test plan and procedures, quality assurance witnesses, a record of all discrepancies, and a test report. Formal testing is always requirements-driven, and its purpose is to demonstrate that the software meets its requirements. Each software development project should have at least one formal test, the acceptance test that concludes the development activities and demonstrates that the software is ready for operations.


Independent Verification and Validation

Independent Verification and Validation (IV&V) is a process whereby the products of the software development life cycle phases are independently reviewed, verified, and validated by an organization that is neither the developer nor the acquirer of the software. The IV&V agent should have no stake in the success or failure of the software. The IV&V agent's only interest should be to make sure that the software is thoroughly tested against its complete set of requirements.